Bond equation of cement ball mill sizing

12 Nov,2015 UTC+8 Views:


 1.Cement ball mill sizing method introduction:

The method is used to size a cement ball mill.

Efficiency correction factors are applied with the Bond equation.

The method is valid both for clinker grinding and for raw materials grinding.

This method only gives a rough and initial idea for sizing a cement ball mill. To go ahead, a deeper study is necessary with ball mills suppliers or a specialized engineering office.

Two calculators have been developed for sizing mono chamber mills and two compartments mills.

2 Bond equation and correction factors:                                                               

 003.jpg        

  

 

       E = specific energy in kWh/t

WI = work index in kWh/t

C = correction factor

P80 = sieve which has 80% of passing in the product

F80 = sieve which has 80% of passing in the feed

Efficiency correction factors are giving by the following equation:                                                                        

 006.jpg                                                          
   
 
C1, a correction for dry grinding,

C2, a correction for open circuit

C3, a correction for mill diameter,

C4, a correction for feed size,

C5, a correction for product fineness,

C6, a correction for high-efficiency separators.

   009.jpg
                           
     
        
The graph below is the basis to get C2:   
   
011.jpg
 
 
 
 
 
 
 
 
 
      
 
 
 
 
014.jpg
 

 

17.jpg

  

 

  

020.jpg

 

 

23.jpg